Decision Gates

Decision Gates

Purpose

Defined moments when you stop, review evidence, and make a deliberate go/no-go choice. Decision gates prevent drift and force re-planning when the plan diverges from reality.

Gate 0 — End of Week 0 (Phase 0 close)

Trigger: end of business Friday Week 0.
Decisions:

Go criteria for proceeding to Phase 1:

If criteria not met: delay Phase 1 by 1 week; escalate blockers via supervisors.


Gate 1 — End of Week 4 (Phase 1 close)

Trigger: end of Friday Week 4.
Decisions:

Go criteria for proceeding to Phase 2:

If criteria not met:


Gate 2 — End of Week 12 (Phase 2 close)

Trigger: end of Week 12.
Decisions:

Go criteria for proceeding to Phase 3:

If criteria not met:


Gate 3 — End of Month 9 (Phase 3 close)

Trigger: end of Month 9.
Decisions:

Go criteria for proceeding to Phase 4:

If criteria not met:


Gate 4 — End of Month 18 (Phase 4 close)

Trigger: end of Month 18.
Decisions:

Go criteria for the next 24 months:


Replan triggers (any time)

If any of these occur outside the gate schedule, stop and replan within one week:

Logging decisions

Every gate decision and replan should be logged in Decisions-Log with:

This becomes the audit trail when you, your supervisors, or future investors ask "why did you do X?"